SkillMaintain manufacturer’s published approach airspeed or in its absence not more than 1.3 VSO, +10/-5 knots with gust factor applied.
From the FAA library
- Chapter 5. Air Traffic Procedures › Section 4. Arrival Procedures › 5-4-21. Missed Approach
radar service is provided, the pilot should conform to radar vectors when provided by ATC in lieu of the published missed approach procedure. (See FIG 5-4-31.) e. Some locations may have a preplanned alternate missed approach procedure ... event the primary NAVAID used for the missed approach procedure is unavailable. To avoid confusion, the alternate missed approach instructions are not published on the chart. However, the alternate missed approach holding pattern will be depicted on the instrument approach…
- Chapter 5. Air Traffic Procedures › Section 4. Arrival Procedures › 5-4-16. Simultaneous Close Parallel PRM Approaches and Simultaneous Offset Instrument A…
Simultaneous Offset Instrument Approach (SOIA). 1. SOIA is a procedure used to conduct simultaneous approaches to runways spaced less than 3,000 feet, but at least 750 feet apart. The SOIA procedure utilizes a straight-in PRM approach ... runway, and a PRM offset approach with glideslope/glidepath to the adjacent runway. In SOIA operations, aircraft are paired, with the aircraft conducting the straight-in PRM approach always positioned slightly ahead of the aircraft conducting the offset PRM approach…
- Chapter 9: Approaches and Landings › Normal Approach and Landing › Final Approach
drift correction is established and maintained to follow a ground track perpendicular to the extension of the landing runway centerline. This requires that the airplane be angled sufficiently into the wind to prevent drifting farther away from the intended landing ... spot. Figure 9-3. Base leg and final approach. Final Approach After the base-to-final approach turn is completed, the pilot aligns the longitudinal axis of the airplane with the centerline of the runway or landing surface…
- Chapter 9: Approaches and Landings › Short-Field Approach and Landing
When safety and conditions permit, a wider-than-normal pattern with a longer final approach may be used. This allows the pilot ample opportunity to adjust and stabilize the descent angle after the airplane is configured and trimmed. A stabilized ... approach is essential. The procedures for landing on a short field or for landing approaches over obstacles as recommended in the AFM/POH should be used. [Figure 9-22 and Figure 9-23] These procedures generally involve a final approach started…
- Chapter 5. Air Traffic Procedures › Section 4. Arrival Procedures › 5-4-3. Approach Control
When radar handoffs are utilized, successive arriving flights may be handed off to approach control with radar separation in lieu of vertical separation. (b) After release to approach control, aircraft are vectored to the final approach course (ILS, RNAV ... issued as required for spacing and separating aircraft. Therefore, pilots must not deviate from the headings issued by approach control. Aircraft will normally be informed when it is necessary to vector across the final approach course for spacing or other…
- Chapter 4: Approaches › Final Approach Segment
Final Approach Segment The final approach segment for an approach with vertical guidance or a precision approach begins where the glideslope/glidepath intercepts the minimum glideslope/ glidepath intercept altitude shown on the approach chart. If ATC authorizes a lower intercept altitude ... final approach segment begins upon glideslope/glidepath interception at that altitude. For a non-precision approach, the final approach segment begins either at a designated FAF, which is depicted as a cross on the profile view, or at the point where…